commissioning: 1929
Павлоград
CCK TM Company supplied and implemented a complex of ventilation equipment for a chemical industry production facility.
The project implemented:
- installation of a compact Airmate suspended air conditioner;
- installation of KROS roof radial fans;
- installation of STAM mounting cups;
- integration of KPU-1N fire dampers into the duct system;
- installation of AVD active vortex deflectors;
- installation of air control devices (air dampers, ventilation grilles).
Implementation result:
- stable air exchange in production premises was ensured;
- the level of fire safety was increased;
- the operation of the ventilation system was optimized;
- compliance with the technical requirements of the facility was ensured.